Re-Building My Studio
ventilation
may 22

i had to remove the plastic pipe that was intended as second ventilation outlet because it was a serious sound leak.

ok...new plan...

so i gathered some stuff and did it all over again with a flexible tube, this time packed in rockwool...

- - - - - - - - - - - - - -

f i n i

( i hope it works now ! )

*
april 22
-

april 20

-

-

-

april 11

- - - - - - - - - - -

april 10

- - - - -

april 6

view from behind the wall

-

-

april 5
- - - - -
april 4

today i worked on one of the main air outlets situated in the corner (see #3 on the drawing below)

it's a box of 60 x 51 cm (height 16 cm) filled with rockwool and a flexible tube (10 cm x 300 cm)

- - - - - - -

april 2

 

1 + 2

tubes to ventilate the space between the inside of the (outside) wall and the floating chamber.

 

- -

-

3

one of the main air outlets

march 22 - march 23 - march 24
- - - - -

- - - -

inside, front -outside, front

march 21
last night and today I worked on the ventilation for the inside (of the floating chamber) as well as outside the chamber (the space inbetween the outside walls and the floating chamber)
here some picts of the ventilation inbetween the outside walls and the chamber

- - - - - - - -

*